Nvidia invests $1.5B in SoftBank data center for OpenAI project

Nvidia invests $1.5B in SoftBank data center for OpenAI project

Key takeaway

  • Nvidia is investing $1.5 billion in SB Energy, a data center developer co-backed by SoftBank and OpenAI, and committing up to $105 billion in credit to build a facility near Cincinnati that will serve as OpenAI's primary compute infrastructure.

  • Nvidia becomes the sole hardware supplier for the project, which will scale from 4.25 gigawatts to 8 gigawatts and rely on a new 9.2 gigawatt natural gas power plant expected to cost $33 billion.

3 Key Points

  1. What happened

    Nvidia announced a $1.5 billion investment in SB Energy, a data center developer backed by SoftBank and OpenAI, and will provide up to $105 billion in credit to build a facility near Cincinnati, Ohio that could scale from 4.25 gigawatts to 8 gigawatts. Nvidia will be the sole supplier of compute infrastructure at the site.

  2. Why it matters

    The investment secures Nvidia's position as the primary hardware vendor for a major infrastructure project supporting OpenAI's operations. SoftBank had previously sold $5.8 billion worth of Nvidia stock in November to fund AI investments, so this partnership signals continued reliance on Nvidia's technology for large-scale AI deployments.

  3. What to watch

    SB Energy will build a 9.2 gigawatt natural gas power plant on the site (land owned by the U.S. Department of Energy) expected to cost $33 billion. Natural gas power plant costs have risen 66% in the last two years, and the new plants may compete for natural gas with export markets in ways that could triple natural gas prices in some parts of the country.

Ask the AI about this article →

FAQ

Where is the data center being built, and what was the site used for before?
The data center is being built near Cincinnati, Ohio on land owned by the U.S. Department of Energy. The site previously enriched uranium for the U.S. nuclear arsenal and for U.S. Navy submarines.
How much power will the facility need, and what is the cost of the power plant?
The data center could scale from an initial 4.25 gigawatts to 8 gigawatts in size. SB Energy will build a 9.2 gigawatt natural gas power plant on the site, expected to cost $33 billion.
Why are power plant costs so high?
Natural gas power plant construction costs have risen 66% in the last two years, according to BloombergNEF.
Yahoo Finance AIRead Original Article

Get the latest AI Business & Industry news every morning

For example, today's edition would include:

  • Visko raises $10M, launches live AI video model OrbisSiliconANGLE AI · 1h ago
  • NVIDIA Leads 5 AI Stocks to Watch in SeptemberYahoo Finance AI · 1h ago
  • UAE AI firm pitches 95% video compression for Saudi securitySemafor Tech · 1h ago

AI-summarized, only the topics you pick — one digest a day via Email, Slack, or Discord.

Free · takes 30 seconds · unsubscribe anytimeWhat is AIToday? →

Ask AI

Ask AI anything about this article. Q&As are published on this page for other readers too.

Related Articles

Next articleAmazon AI facility secretly ordered 1,000 rare books for scanning