Microsoft and Chevron signed an exclusivity agreement to develop an integrated data center and power plant complex in West Texas
The facility will initially operate at 2.5 gigawatts of power capacity with potential to expand to 5 gigawatts
The colocated campus design combines computing infrastructure with dedicated power generation to support large-scale AI operations
This partnership addresses the critical challenge of securing sufficient reliable energy to power energy-intensive AI data centers