JERA courts Anthropic, Meta, Amazon, Microsoft, Google for Tokyo data centers

Send on LINE
JERA courts Anthropic, Meta, Amazon, Microsoft, Google for Tokyo data centers

3 Key Points

  1. What happened

    JERA opened exploratory talks with Anthropic, Meta, Amazon, Microsoft and Google to colocate AI data centers at its Tokyo-area power plants, Nikkei Asia reported; no formal agreement has been signed.

  2. Why it matters

    Colocating lets a buyer draw electricity directly from the plant rather than wait years for high-voltage transmission upgrades, a time advantage JERA is pitching to the five hyperscalers.

WHO IT HITSThis lands on AI infrastructure planners at the five hyperscalers and on JERA's thermal plant operators, who would host the data centers and supply power directly, potentially bypassing grid queues.

Not sure about something? Ask the AI

Questions and answers are published on this page.

Summaries like this, every morning.

Context & Analysis

JERA's move comes as AI companies seek ways to secure power quickly. The company runs more than 20 thermal power plants with an estimated combined capacity of almost 55 GW, giving it land and generation assets that can be paired with data centers. The October 1 memorandum with Dell Technologies and Rhaelm for a 400-megawatt-class facility at Chiba serves as a template: total investment is expected to exceed $15 billion, about 2.3 trillion yen, and phased operations are targeted for 2028. Apollo Global Management is backing Rhaelm as a strategic investor.

The pitch to hyperscalers rests on time. Colocating directly next to generation lets a buyer draw electricity straight from the plant rather than wait years for high-voltage transmission upgrades, according to DatacenterDynamics. JERA's Global CEO and Chairman, Yukio Kani, says the company's LNG value chain gives AI infrastructure 'access to the large-scale, reliable energy it needs.'

Neither Anthropic nor Meta has publicly confirmed the negotiations, and no formal agreement with any of the hyperscalers has been signed. The talks sit alongside a draft Japanese AI law that would allow on-site inspections of OpenAI and Anthropic, the same labs JERA is courting as power customers.

FAQ
Which companies are in talks with JERA?
JERA has entered exploratory talks with Anthropic, Meta, Amazon, Microsoft and Google, according to Nikkei Asia.
What is the first project under this model?
On October 1, JERA, Dell Technologies and Rhaelm signed a memorandum for a 400-megawatt-class AI data center on land next to the Chiba thermal plant, with phased operations targeted for 2028.
How much investment is expected for the Chiba project?
Total investment is expected to exceed $15 billion, about 2.3 trillion yen, across land, power infrastructure, construction and AI compute.
Send on LINE

Also reported by DIGITIMES Asia

AI news that matters for your work, delivered every morning.

Pick your industry and the AI tools you use, and get news related to your work every day.

Free · 30 seconds with Google · unsubscribe anytimeWhat is AIToday? →

Ask AI

Ask AI anything about this article. The AI reads this article, earlier AIToday articles, and Wikipedia, and cites its sources. Q&As are published on this page for other readers too.

Questions and answers are published on this page.