SoftBank's $7.1 billion loss caps AI gas turbine bet

Send on LINE
SoftBank's $7.1 billion loss caps AI gas turbine bet

3 Key Points

  1. What happened

    SoftBank posted a $7.1 billion quarterly loss on Tuesday, with over half from power-equipment write-downs after over-ordering 13 gigawatts of gas turbines — almost 50% more than needed.

  2. Why it matters

    The costly lesson suggests natural gas may be less of a sure thing for AI data centers than assumed, with grid connections and batteries emerging as alternatives.

WHO IT HITSData center developers and hyperscalers planning on-site gas generation may rethink reliance on turbine reservations, as the losses highlight the risk of over-ordering equipment years in advance.

Not sure about something? Ask the AI

Questions and answers are published on this page.

Summaries like this, every morning.

Context & Analysis

SoftBank's aggressive procurement strategy, ordering more than 13 gigawatts of gas turbines — almost 50% more than needed — was an attempt to corner a portion of the power market as AI data centers raced to secure electricity. The bet was that by deploying its significant war chest, SoftBank could become a key supplier to an AI world hungry for power. But the $7.1 billion quarterly loss, with over half tied to power-equipment write-downs, shows that the market did not develop as expected. Turbine order queues now stretch into the early 2030s, and the swiftness of AI's power demand caught the energy world off guard. As data center operators gain more experience, they may increasingly favor grid connections and large batteries over natural gas, which carries risks like winter curtailments. The magnitude of SoftBank's loss — over $3 billion — reflects the electricity mania, but it is unlikely to trigger mass cancellations of gas plants, as AI's power demand remains too large. Still, SoftBank may have found the ceiling for natural gas in the AI boom.

FAQ
How big was SoftBank's loss?
SoftBank announced a $7.1 billion quarterly loss on Tuesday, with over half stemming from power-generating equipment.
Why did SoftBank over-order turbines?
SB Energy overbooked turbines to secure them quickly, as CEO Peter Gardett of Noreva said it had no choice if it wanted turbines right away.
What are the alternatives to natural gas for data centers?
Brent Nelson of Ascend Analytics suggested grid connections and large batteries as cost-effective options to manage peak loads and curtailment.
Send on LINE

AI news that matters for your work, delivered every morning.

Pick your industry and the AI tools you use, and get news related to your work every day.

Free · 30 seconds with Google · unsubscribe anytimeWhat is AIToday? →

Ask AI

Ask AI anything about this article. The AI reads this article, earlier AIToday articles, and Wikipedia, and cites its sources. Q&As are published on this page for other readers too.

Questions and answers are published on this page.

Related Articles

Next articlePodqi study: Perplexity cites risky retail sites in 15% of answers