What happened
Drax, Brookfield and Radiant will jointly develop more than 1GW of AI data centre capacity at Drax Power Station, with Brookfield estimating over £20 billion ($26.8 billion) in investment if built in full; Drax shares jumped more than 8%.
Why it matters
Phase one commits only £2.5 billion for up to 100 MW live by Q1 2028, with a further 500 MW slated for 2028–2031, so the headline total rests on later phases that still need planning permission and a separate ministerial sign-off on 500 MW of Drax's biomass CfD.
What to watch
Public consultation on the planning application is expected to begin in November 2026.
WHO IT HITSUK energy and infrastructure planners, plus the data centre operators and AI compute buyers who would occupy the campus, get a rare site with a 4 GW grid connection and 2.6 GW of dispatchable generation already in place — though no anchor tenant has been named, so the demand side remains open.
Summaries like this, every morning.
The project is being sold on the grid, not the land. Drax Power Station already has a 4 GW connection and 2.6 GW of dispatchable generation on site, and existing Drax generation would supply round-the-clock power to the data centre under a long-term power purchase agreement. That is the pitch CEO Will Gardiner made: the station is one of the few UK sites that can provide large-scale reliable power directly to data centre customers by utilising existing and underutilised generation capacity.
The money is staged accordingly. Phase one targets up to 100 MW live by the first quarter of 2028 behind an initial £2.5 billion, and a further 500 MW is slated to come online between 2028 and 2031, with the partners looking to secure more than 1 gigawatt at the site longer term. The £20 billion ($26.8 billion) figure is Brookfield's estimate for the full build, not a committed sum.
Two constraints sit outside the partners' control. Redirecting 500 MW covered by Drax's existing biomass CfD requires a separate government minister sign-off, adding regulatory friction beyond standard planning approvals. And the planning application is still being prepared, with public consultation expected to begin in November 2026. JPMorgan analysts argued the announcement raised confidence that the station will continue operating beyond March 2031, when Drax's current subsidy scheme expires.
Pick your industry and the AI tools you use, and get news related to your work every day.
Free · 30 seconds with Google · unsubscribe anytimeWhat is AIToday? →
Ask AI anything about this article. The AI reads this article, earlier AIToday articles, and Wikipedia, and cites its sources. Q&As are published on this page for other readers too.
At the Dell Technologies New York Symposium, Dell CTO John Roese said the moat in AI systems is not the tools…
IDC's Worldwide Future of Work Survey (May 2026) found the majority of "leaders" — organizations reporting 50%…

ABB and SynerLeap named Wasome winner of the ABB Startup Challenge China 2026, awarding a 200,000 CNY (about $…

Anthropic debuted on the Nasdaq Thursday, initially raising $81.3 billion at a price of $83 per share, then bo…

In its 2026 sustainability report, Meta said it is re-evaluating the 2030 timeframe for its net-zero goal, aft…

American Banker published exclusive research examining how JPMorgan's AI strategy is putting governance to the…